Renovation case study

Full Property Renovation

End-to-end renovation of a four-storey Chelsea townhouse — structural opening-up, full re-wire, new heating system, kitchen, two bathrooms and complete redecoration.

Location
Chelsea, London
Programme
11 weeks
Budget
£128,000
Full Property Renovation after
Full Property Renovation before
BEFOREAFTER

Overview

End-to-end renovation of a four-storey Chelsea townhouse — structural opening-up, full re-wire, new heating system, kitchen, two bathrooms and complete redecoration.

The Challenge

The property had been let for over a decade and required modernisation throughout, including dated electrics that no longer met current regs, a tired galley kitchen and poorly insulated rear extension.

Our Solution

Single project manager coordinating structural engineer, electricians, plumbers, kitchen fitters, plasterers and decorators. Phased programme to keep the client informed and the build clean week-on-week.

The Outcome

Delivered on the agreed completion date, fully signed-off by Building Control. EPC rating improved from D to B.

"A complete kitchen and flooring transformation in our Chelsea townhouse. Project-managed to perfection — every trade arrived when they said they would."
Sophia Allen
Homeowner, Chelsea